A14 Closures June 2019

A14 Update:

The new westbound off-slip at Junction 28, Cambridge Services/Swavesey, will open in early June.

Changes will be made to the layout of Junction 29, Bar Hill on 8 June, moving traffic from the existing bridge onto one of the newly installed bridges. This will allow the earthworks on the second bridge in the new Bar Hill gyratory to be completed. A full closure from Junction 28 to Junction 30 will follow on Saturday 22 and Sunday 23 June for demolition of the old Bar Hill bridge. Construction of the new A14 carriageway and local access road between Swavesey and Bar Hill continues apace. More information can be found on Highways England website.

A weekend closure of Dry Drayton bridge is scheduled for the weekend beginning Friday 14 June. Should work be completed we will remove the temporary traffic lights.

Preparatory work for the widening of the eastbound off slip at Junction 32, Histon has now started, including moving the traffic lane guard. Work at junction 32 roundabout will soon begin on the Bridge Road exit.

Following agreement with the local authority, piling works beside Impington bridge, adjacent to the guided busway will take place during daytime hours rather than at night. This will start soon.

 