ROADWORKS – Resurfacing Bar Hill Village Roundabout – 14-18 December

ROADWORKS RESURFACING BAR HILL VILLAGE ROUNDABOUT
A14 Cambridge to Huntingdon Improvement Scheme
Night-time traffic lights – A14 / Crafts Way / Saxon Way Roundabout
14 December 2020 to 18 December 2020, 4 consecutive nights
2100 – 0500 hours each night

Where: The Crafts Way / Saxon Way roundabout closest to the A14.

What: Highways England will be resurfacing the roundabout and painting fresh white lines around it.

Why: To do this safely they will need to close one of the lanes around the junction. Therefore, to maintain access for residents and minimise the impact during the day, the work has been scheduled to take place at night.

Please do note that during the works they will be using 4-way traffic light control on each of the
legs of the roundabout, so if you are out overnight you may be delayed for a few minutes.
It is hoped that these works will not cause a noise disturbance, but to mitigate this as much as possible activities will be planned to happen closest to properties as early in the night shift as possible.

A14CambridgeHuntingdon@highwaysengland.co.uk Monday – Friday.
Customer contact centre on 0300 123 5000 which is operational 24 hours a day.
Additional details of the scheme can also be accessed at:
http://www.highways.gov.uk/roads/road-projects/A14-Cambridge-to-Huntingdon-Improvement-Scheme